Georgia Data Centers

  • Atlanta’s 56 Marietta Street carrier hotel anchors the Southeast’s most important interconnection point, with ' . number_format($total) . ' tracked facilities statewide.
  • Georgia’s sales tax exemption on data center equipment and electricity saves qualifying operators millions per facility annually — one of the most generous incentive programs in the country.
  • Google, Meta, and Microsoft are building massive hyperscale campuses on former farmland in Newton County, east of Atlanta.

Atlanta’s Carrier Hotel and the Push to Newton County

Georgia’s data center story starts at 56 Marietta Street in downtown Atlanta — a carrier hotel that has served as the Southeast’s primary interconnection point for two decades. Operators cluster along the I-285 perimeter in Fulton County and extend into Douglas County (Lithia Springs) and DeKalb County. But the biggest new development is happening 50 miles east in Newton County around Social Circle, where Google, Meta, and Microsoft are building hyperscale campuses on hundreds of acres of former agricultural land with access to Georgia Power’s competitive industrial rates.

County-Level Breakdown

Georgia’s ' . $county_count . ' data center counties reflect two eras: the legacy Atlanta metro market clustered around Fulton and Douglas counties, and the newer hyperscale corridor extending east along I-20 into Newton and Walton counties. Atlanta’s density comes from enterprise colocation; the eastern buildout is almost entirely hyperscale cloud and AI infrastructure.

CountyFacilitiesCapacity (MW)Top Operators
Fulton832,05211:11 Systems, 365 Data Centers, Lincoln Property Company +57 more
Douglas27923Amazon Web Services, Aligned Data Centers, CoreWeave +16 more
Newton13365Amazon Web Services, Universal Planning, Meta +3 more
Cobb11109365 Data Centers, American Tower, Coloblox Data Centers +7 more
Fayette92,482Microsoft, T5 Data Centers, Quality Technology Services +1 more
Gwinnett820CleanSpark, Inc., CoreWeave, Flexential +4 more
Coweta63,580Amazon Web Services, McKagen Jones / Bridgeport Industrial, LDO Coweta LLC +3 more
Columbia61,800Google, Hampton Technology Park, Cloverleaf Infrastructure +1 more
Whitfield5507CleanSpark, Inc., Core Scientific
Muscogee51,270Georgia Data Center, DLI ONE, Duos Edge AI (Duos Technologies Group) +2 more
Bartow52,612DataBank, Thor Equities, Taurus Investment Holdings (Taurus DC SPE LLC); to be managed by Digital Realty +2 more
DeKalb4—Emory University, Lumen Technologies, Uniti Wholesale
Troup4364Google, KDC, Wattum Management
Spalding4450Industrial VI Enterprises, Montana Property Group, Wallace Jackson LLC +1 more
Clayton3—Delta Air Lines, Digital Realty
Richmond3—QTS Data Centers
Washington3405CleanSpark, Inc., CleanSpark, Mawson Infrastructure Group
Henry3240Equinix, Southeast Property Holdings, Surge Development LLC
Monroe32,220Google, Cloverleaf Infrastructure, Trammell Crow Company (CBRE)
Floyd2504Microsoft, Atlas Development
Early21,000QTS Data Centers
Rockdale2432DC BLOX
Twiggs2500Eagle Rock Partners
Butts2250Amazon Web Services, River Park Industrial LLC
Effingham13,200OpenAI
Clarke1—University of Georgia
Lamar1—Amazon Web Services
Hall1—Project Turbo LLC
McDuffie1400Project Turbo LLC
Irwin11,200Unknown
Jackson1—Northern Data
Wilkes136CleanSpark, Inc.
Carroll1—Atlas Development
Randolph17LN Compute Inc.
Bulloch1—4AM Development
Treutlen150Cango Inc. (GreenVolt Technology LLC)
Walker1—CleanSpark, Inc.
Emanuel1—CleanSpark, Inc.
Forsyth1—UPS

Google, QTS, and the Hyperscale Land Rush

Google’s operations in Newton and Douglas counties represent billions in cumulative investment. QTS (Blackstone) operates one of the largest colocation portfolios in the Atlanta metro, while Switch, DataBank, and T5 Data Centers serve the enterprise segment. The hyperscale buildout has shifted Georgia’s operator mix — five years ago the market was primarily colocation; now the largest facilities are single-tenant cloud campuses.

#OperatorFacilitiesCapacity (MW)Locations
1Microsoft91,938Rome, Douglasville, East Point, Fayetteville
2QTS Data Centers92,164Atlanta, Duluth, Augusta, Blakely
3T5 Data Centers8520Palmetto, Newnan, Atlanta, Lithia Springs
4DataBank8370South Fulton, Atlanta, Lithia Springs, Cartersville
5Google82,300Appling, Douglasville, Evans, Atlanta
6CleanSpark, Inc.766College Park, Dalton, LaFayette, Norcross
7Digital Realty7—Atlanta, Austell, Forest Park
8Lumen Technologies6—Atlanta, College Park, Doraville
9Vantage Data Centers5—College Park, Douglasville, South Fulton
10Flexential523Alpharetta, Douglasville, Norcross
11Meta5365Zcta 30025, Social Circle
12Amazon Web Services5—Jackson, Covington, Newnan, Douglasville
13DC BLOX4672Conyers, Lithia Springs
14STACK Infrastructure4228Alpharetta, Lithia Springs
15Core Scientific4507Dalton
16Quality Technology Services4—Fayetteville, Smiths Crossroads, Suwanee
17Serverfarm3—Suwanee, Covington
18EdgeConneX3326Union City, Atlanta
19TPA Group3—Covington, Social Circle
20Equinix3240Atlanta, Vinings, Hampton
21CoreWeave3100Alpharetta, Atlanta, Douglasville
22Coloblox Data Centers3—Atlanta, Marietta
23Atlas Development3936Villa Rica, Rome, Adairsville
24Ascent29Alpharetta
25Switch2—Lithia Springs, Cartersville

Georgia’s Largest Facilities by Capacity

The scale of Georgia’s newest builds dwarfs the legacy Atlanta market. ' . htmlspecialchars($cap_names[0]) . ' County alone accounts for ' . number_format($top_cap[$cap_names[0]]["cap"]) . ' MW of tracked capacity, driven by hyperscale AI training infrastructure that didn’t exist five years ago. Georgia Power has filed resource plans specifically citing these facilities as a primary growth driver.

#FacilityOperatorLocationCapacityStatus
1OpenAI Project CameliaOpenAISpringfield, Effingham Co.3,200 MWPlanned
2Project Bunkhouse (Taurus/Digital Realty Data Center Campus)Taurus Investment Holdings (Taurus DC SPE LLC); to be managed by Digital RealtyStilesboro, Bartow Co.1,830 MWPermitted
3Microsoft Fairwater Atlanta (Azure AI Superfactory)MicrosoftFayetteville, Fayette Co.1,500 MWOperational
4Bridgeport Revised Data Center CampusMcKagen Jones / Bridgeport IndustrialMoreland, Coweta Co.1,500 MWPlanned
5Google Columbia County CampusGoogleAppling, Columbia Co.1,200 MWPlanned
6Project ArrowheadUnknownOcilla, Irwin Co.1,200 MWPlanned
7Rumble Technology ParkCloverleaf InfrastructureForsyth, Monroe Co.1,120 MWPlanned
8Google Monroe County CampusGoogleForsyth, Monroe Co.1,100 MWPlanned
9QTS Project Blue HoleQTS Data CentersBlakely, Early Co.1,000 MWPermitted
10Project Sail – Prologis Data Center CampusPrologisNewnan, Coweta Co.900 MWPermitted
11Project Peach (CyrusOne Palmetto)CyrusOne / North Coweta InvestorsPalmetto, Coweta Co.700 MWPlanned
12Project Ruby (Columbus)Habitat Real Estate PartnersColumbus, Muscogee Co.650 MWPlanned
13QTS Fayetteville CampusQTS Data CentersFayetteville, Fayette Co.636 MWOperational
14Columbus Georgia Data CenterGeorgia Data CenterColumbus, Muscogee Co.600 MWPlanned
15Hampton Technology Park AugustaHampton Technology ParkGrovetown, Columbia Co.600 MWPlanned
16Project Sassy (Atlas Development Rome)Atlas DevelopmentRome, Floyd Co.504 MWPlanned
17Eagle Rock Wildcat Ridge (Twiggs Co.)Eagle Rock PartnersJeffersonville, Twiggs Co.500 MWPlanned
1875 South Data Center CampusIndustrial VI EnterprisesGriffin, Spalding Co.450 MWPlanned
19Project Springbank (Atlas Bartow)Atlas DevelopmentAdairsville, Bartow Co.432 MWPlanned
20Project Azalea Data Center CampusProject Turbo LLCThomson, McDuffie Co.400 MWPermitted
21Meta Social Circle / Newton CampusMetaSocial Circle, Newton Co.365 MWPlanned
22PRL2 (KDC/Google LaGrange Expansion)KDCLaGrange, Troup Co.350 MWPlanned
23TA Realty Atlanta (ATL03/Red Oak)TA RealtyUnion City, Fulton Co.324 MWPlanned
24Project Steamboat (Microsoft Union City)MicrosoftUnion City, Fulton Co.324 MWPlanned
25EdgeConneX ATL11-13EdgeConneXUnion City, Fulton Co.324 MWPlanned

Tax Incentives Keep Georgia’s Pipeline Full

Georgia’s High-Technology Tax Exemption waives state sales tax on data center equipment and electricity for facilities investing at least $15 million over five years. That incentive — worth millions per facility annually — continues to attract new entrants alongside the state’s competitive 6–7¢/kWh industrial rates. Google’s Newton County campus, Meta’s Stanton Springs project, and QTS’s Atlanta metro expansion add hundreds of megawatts to a pipeline of ' . number_format($pipeline) . ' facilities statewide.

Georgia Power’s Regulated Rates and Industrial Tariffs

Georgia’s electricity market is fully regulated under Georgia Power (a Southern Company subsidiary) — no retail choice, but stable, predictable pricing. Industrial rates average 6–7¢/kWh, among the lowest in the Southeast. Data centers benefit from dedicated Large Industrial Service tariffs with demand charges that reward consistent, high-load-factor consumption. Georgia Power has added significant natural gas and solar generation specifically to meet data center growth, filing a 2025–2028 Integrated Resource Plan that includes over 6,000 MW of new capacity. Compare current Georgia electricity rates across service territories.

Frequently Asked Questions

What tax incentives does Georgia offer data centers?

Georgia exempts qualifying data centers from state sales tax on equipment purchases and electricity through the High-Technology Tax Exemption. To qualify, facilities must invest at least $15 million over 5 years and create at least 25 new jobs. The exemption applies to servers, cooling equipment, generators, UPS systems, and the electricity consumed by the facility.

Why is Atlanta a major data center market?

Atlanta is the economic and connectivity hub of the Southeast. The city’s carrier hotel at 56 Marietta Street is a critical interconnection point, and its position as an airline and logistics hub translates to dense fiber routes. Georgia Power offers competitive industrial rates, and the state provides generous tax exemptions.

Where are hyperscale data centers being built in Georgia?

Newton County (Social Circle area) has become Georgia’s hyperscale corridor, with Google, Meta, and Microsoft building massive campuses on hundreds of acres of former farmland. Douglas County (Lithia Springs) hosts major QTS and Google facilities. These locations offer abundant land, Georgia Power backbone transmission access, and proximity to Atlanta’s fiber networks.

How much electricity do Georgia data centers use?

Georgia’s data centers consume an estimated 9 TWh annually, roughly 6% of the state’s total electricity. With the current construction pipeline, Georgia Power projects data center load could grow by 50–80% over the next five years, driven primarily by hyperscale AI training facilities.

Is Georgia Power prepared for data center growth?

Georgia Power has filed a 2025–2028 Integrated Resource Plan that includes over 6,000 MW of new generation capacity — a mix of natural gas, solar, and battery storage — specifically citing data center demand as a primary growth driver. The utility has also invested in dedicated transmission corridors to Newton County.

How many data centers are in Georgia?

Georgia has 230 tracked data center facilities across 39 counties. The vast majority are concentrated in the Atlanta metropolitan area and the emerging Newton County hyperscale corridor east of the city.